Ninth and final uranium shipment reaches Rooppur as second grid test continues

Priyo News 24 Desk · Pabna

Published: · 3 min read

Ninth and final uranium shipment reaches Rooppur as second grid test continues
Illustration: Priyo News 24
Photo: IAEA Imagebank / flickr (CC BY 2.0)

At a glance

  • The ninth and final uranium shipment has reached the Rooppur Nuclear Power Plant.
  • Four shipments, from the sixth to the ninth, arrived in about two weeks.
  • Unit 1 is in its second phase of trial power supply to the national grid.

The Rooppur uranium deliveries are complete. The ninth and final shipment of nuclear fuel has reached the Rooppur Nuclear Power Plant at Ishwardi in Pabna, according to reports published on Friday, 27 November, by Jugantor, Kaler Kantho, Amar Sangbad, Desh Rupantor, Sangbad and Views Bangladesh, among others.

The consignment arrived while the plant's first unit is supplying electricity to the national grid on a trial basis. Asia Daily and Barlekha Today reported that the second phase of that trial supply is still continuing.

What we know

  • What: The ninth uranium shipment has reached Rooppur, and it is the last one.
  • Where: Ishwardi, Pabna, at the project site on the bank of the Padma river.
  • When: Reported on Friday, 27 November.
  • Status now: Unit 1 is in the second phase of trial power supply to the national grid.

The exact amount of fuel in the final consignment could not be confirmed from more than one source. This story will be updated if the project authority releases details.

Four shipments in two weeks

The last shipments came in quick succession. Bangladesh Pratidin's English edition reported the sixth shipment on 14 November. The seventh was reported by the Dhaka Tribune and The Daily Observer. The eighth reached the plant on 24 November, as Daily Waadaa and TOB News reported. Three days later came the ninth and final consignment.

Why the plant needs uranium

A nuclear plant uses uranium instead of coal or gas. Inside the reactor, uranium atoms split (fission) and release a great deal of heat. That heat turns water into steam, the steam spins a turbine, and a generator produces electricity.

A reactor needs fuel for its first loading and a reserve for later refuelling, which is why the fuel was brought from Russia in stages. With the final shipment in, that planned delivery phase is over.

Timeline

  • 2023: The first uranium shipment for Rooppur arrives from Russia.
  • 14 November 2026: The sixth shipment arrives.
  • 17 November: Unit 1 connects to the national grid for the first time, starting at 350 MW.
  • 18 November: The first test phase ends after about 8.5 hours of supply.
  • 23 November: The second phase of trial supply begins.
  • 24 November: The eighth shipment arrives.
  • 27 November: The ninth and final shipment is reported.

Rooppur at a glance

  • Total capacity: 2,400 MW from two units of 1,200 MW each.
  • Technology: Russian VVER-1200 reactors, built with the state corporation Rosatom.
  • Significance: Bangladesh's first nuclear power plant.

What it means for ordinary people

Rooppur's power is not yet part of the regular supply, so people should not expect an immediate change in load-shedding or electricity bills. Still, the arrival of all the fuel and the ongoing grid tests show the plant moving one step closer to commercial operation.

A nuclear plant burns no coal or gas while running, so its emissions during generation are very low. Because a small amount of fuel produces power for a long time, it could in future ease some of the pressure from imported LNG and coal.

What happens next

Output is to be raised step by step in later test phases. No official date has yet been announced for Unit 1 to start regular operation at full capacity. Priyo News 24 will update this story when new information comes in.

FAQ

When did the final uranium shipment reach Rooppur?

Several outlets, including Jugantor, Kaler Kantho, Amar Sangbad, Desh Rupantor and Views Bangladesh, reported on Friday, 27 November, that the ninth and final shipment had reached the plant.

How many uranium shipments has Rooppur received?

According to the reports, the final consignment was the ninth, so the fuel arrived in 9 shipments in total.

Is Rooppur supplying electricity regularly now?

No. Unit 1 was connected to the national grid for the first time on 17 November. Its second phase of trial supply is under way; regular commercial operation has not started yet.

What is the capacity of Rooppur Nuclear Power Plant?

2,400 MW in total from two units of 1,200 MW each.

Sources

This report was written in our own words after checking facts across several reliable sources.

  1. Jugantor
  2. Kaler Kantho
  3. Amar Sangbad
  4. Desh Rupantor
  5. Sangbad
  6. Views Bangladesh
  7. Asia Daily
  8. Barlekha Today
  9. Daily Waadaa (eighth shipment)
  10. TOB News (eighth shipment)
  11. Dhaka Tribune (seventh shipment)
  12. The Daily Observer (seventh shipment)
  13. Bangladesh Pratidin English (sixth shipment)

Comments

Text only — no links allowed · /1000

No comments yet — be the first to comment.

Get the latest news by email

New stories and articles land in your inbox as soon as they are published. Stop any time with one click.