Rooppur Nuclear Power Plant reconnects to national grid for second trial supply
At a glance
- Rooppur's first unit is back on the national grid in a second round of testing.
- Its first connection on November 17 brought 350MW; that test ended after about 8.5 hours.
- Output will rise in steps, with full capacity targeted in the first half of next year.
The Rooppur Nuclear Power Plant has started supplying electricity to the national grid on a trial basis for the second time. Jamuna Television, The Business Standard Bangla, Amar Desh, Daily Sangram, Sangbad Porikrama and other outlets reported the news on Monday (November 23).
It moves the first unit of Bangladesh's first nuclear power plant, at Ishwardi in Pabna, to the next stage of commissioning. The unit had been disconnected on November 18 after its first round of testing.
What happened
Confirmed so far from combined reports:
- What: Rooppur's first unit is feeding the national grid again.
- Type: This is a trial supply, not regular or commercial generation.
- Round: It is the second time the unit has been connected to the grid.
How many megawatts are going to the grid in this round, and how long the test will run, could not yet be confirmed by more than one outlet. This story will be updated when official figures are available.
What happened in the first round
On Tuesday, November 17, Rooppur's first unit was connected to the national grid on a trial basis for the first time. Dhaka Tribune, World Nuclear News and other outlets reported that 350MW reached the grid in the first stage, the first electricity ever produced from nuclear power in Bangladesh. Dhaka Tribune wrote that day that Bangladesh had become the world's 33rd nuclear power nation.
After supplying power for about 8.5 hours, the unit was disconnected from the grid. Jugantor and Bangla Tribune reported at the time that the first test round had been completed successfully and that testing would continue. Today's connection is that next round.
Why testing happens in rounds
A new nuclear unit is not run at full power continuously from the start. During commissioning, the reactor is started and stopped several times, with different tests in each round:
- Grid synchronisation: checking that the generator's output matches the national transmission system.
- Equipment behaviour: seeing how the turbine, generator and safety systems perform under load.
- Raising output: increasing power a little in each round, within safe limits.
Data from each round is analysed before the next one starts. Connecting, disconnecting and connecting again is a normal part of this process.
Timeline
- November 17: first connection to the national grid, starting with 350MW.
- November 18: first test round ends after about 8.5 hours of supply; unit disconnected.
- November 23: several outlets report that the second trial supply has begun.
Rooppur at a glance
- Location: Ishwardi, Pabna, on the bank of the Padma river.
- Total capacity: 2,400MW from two units of 1,200MW each.
- Technology and builder: Russian VVER-1200 reactors, built by the state company Rosatom.
What it means for ordinary people
Rooppur's electricity is not yet part of regular supply, so no immediate change in load-shedding or power bills should be expected. But each successful round moves the plant closer to commercial operation. Earlier reports mentioned a target of running the first unit at full capacity in the first half of next year, before or during the summer peak in demand. At that point the unit alone would provide 1,200MW.
What happens next
Output is expected to rise step by step as testing continues. Priyo News 24 will update this story when official details of this round's output and duration are released.
Sources
This report combines coverage from Jamuna Television, The Business Standard Bangla, Amar Desh, Daily Sangram, Sangbad Porikrama and Daily Bangla Post, plus earlier reports on the first round by Jugantor, Bangla Tribune, Dhaka Tribune and World Nuclear News. Only facts confirmed by more than one source are included.
FAQ
Has Rooppur been connected to the national grid again?
Yes. Jamuna Television, The Business Standard Bangla, Amar Desh, Daily Sangram and other outlets reported that a second trial supply to the national grid has begun.
When was Rooppur first connected to the grid?
On Tuesday, November 17, 2026. The first stage brought 350MW to the grid. After about 8.5 hours of supply, the first test round ended and the unit was disconnected.
Will Rooppur electricity now be available regularly?
No, this is still a trial supply. During commissioning, a new unit is tested in several rounds and its output is raised step by step; commercial operation comes later.
How much power will Rooppur produce at full capacity?
The plant's total capacity is 2,400MW from two units of 1,200MW each. Reports have mentioned a target of running the first unit at full capacity in the first half of next year.